Knik Construction - General Heavy Construction Company Specializing in Remote-Site ProjectsGeneral Heavy Construction

 

Airport Project

Bethel Airport Phase III, Stage II

Location: Bethel, Alaska

Project Dates: 2008-2009

Owner: State of Alaska Department of Transportation and Public Facilities

Contract Amount: $9,745,022

Status: Complete

Project Details: The project consisted of the completion of a new parallel runway and three taxiways. Additional work involved installation of a new standby generator module and underground fuel storage tank de-commissioning; airport primary electrical service, new runway lighting, roughed in FAA navigational aids on new pads; repair and stabilization of eroded Stage 1 embankment side-slopes and construction of an apron interconnect.